Covina Metrolink Access Connectivity Project - Federal Project No. HIPL- **** ( 023) - Project ****
AI helper
The project must be completed within 60 working days from the notice to proceed. The notice states: the successful bidder contractor shall complete all work under the contract within sixty 60 working days from the notice to proceed.
Progress payments are subject to 5% retention. The notice states: five percent 5 of any progress payment will be withheld as retention.
Bidders must be registered with the Department of Industrial Relations and possess a valid Class A contractor's license. The notice states: no contractor or subcontractor shall be qualified to bid on. . . unless currently registered and qualified to perform public work pursuant to section **** and each bidder shall possess a valid class a contractors license.
Liquidated damages of $500 per day for incomplete work. The notice states: Liquidated damages shall accrue in the amount of 500 for each day that work remains incomplete beyond the project completion deadline.
Failure to enter into the contract within 15 days after award notice may forfeit bid security. The notice states: failure to enter into the contract with the city. . . within fifteen 15 days after the date of the mailing of written notice of contract award. . . shall subject the bid security to forfeiture.
The city engineer estimates the value of the work at $1,200,000. The notice states: the city engineer estimates the value of the work to be 1, 200, 000.