Demolition and ACM abatement project across 11 sites in Aurora, CO. Mandatory pre-bid conference and site visit on Nov 18, 2026. Bids due Dec 10, 2026 via Bidnet. Bid bond of 5% required. Questions due Nov 30, 2026. Substantial completion by July 30, 2027, final by Aug 27, 2027. Liquidated damages $500/day. 80% Colorado labor required. SBE program applies for contracts over $250,000.
The work must be substantially complete by July 30, 2027, with final completion by August 27, 2027. As stated: all work be substantially complete by july 30, 2027, with final completion by august 27, 2027.
Payments are made through electronic transfers. The successful bidder must complete the ACH direct payment authorization form upon contract award. As stated: the city now makes payments through electronic transfers.
The contract will be awarded to the lowest responsible bidder. As stated: it is the intent of the city to award a contract to the lowest responsible bidder.
Bidders must have successfully abated asbestos and conducted at least 3 building demolition projects. Key personnel need 5 years of experience. As stated: successfully abated asbestos containing material and conducted a minimum of 3 building demolition projects.
Liquidated damages are $500 per day for failure to complete the work as prescribed. As stated: subject to liquidated damages which are **** per day.
A mandatory in-person pre-bid conference and site visit will be held on November 18, 2026, at 8:00 a. m. As stated: prebid conference and site visit mandatoryinperson.
Questions must be submitted in writing by email to heidi ellis no later than 2:00 p. m. on November 30, 2026. As stated: must be received no later than 2: 00 p. m. , local time, november 30, 2026.
Bids not accompanied by the required bid bond will be considered nonresponsive and rejected. Also, failure to submit SBE forms within 3 working days may result in rejection. As stated: bids not accompanied by appropriate bid bond will be considered nonresponsive and shall be rejected.
The estimated cost for this project is from $1,345,**** to $1,550,****. As stated: the estimated cost for this project is from 1, 345, **** to 1, 550, ****.