Sealed bids for Route 130 & 210 water line project due November 19, 2026, at 2:00 PM. Work includes installing water lines and appurtenances. Bid security of 5% required. Optional prebid conference on October 13, 2026. Bids submitted electronically via eVA. Project funded with federal and state money, subject to Davis-Bacon and other federal requirements. Contract A and B, with option to award to different bidders if in owner's interest.
The work will be substantially complete within 180 days and completed and ready for final payment within 210 days after the contract times commence. the work will be substantially complete within 180 days after the date when the contract times commence to run
Progress payments are made monthly, with 95% of the value of work completed, less retainage. 95 percent of the value of the work completed with the balance being retainage.
The contract will be awarded to the responsible bidder submitting the lowest responsive bid. such award will be to the responsible bidder submitting the lowest responsive bid.
Bidders must submit written evidence of qualifications, including financial data, previous experience, and present commitments, within 5 days of owner's request. bidder must submit the following information: a. written evidence establishing its qualifications such as financial data, previous experience, and present commitments.
Liquidated damages are $1,000 per day for delay in substantial completion and $500 per day for delay in completing remaining work. contractor shall pay owner 1, 000 for each day that expires after the time. . . for substantial completion
Bidders are required to visit the site and conduct a thorough visual examination. Bidder is required to visit the site and conduct a thorough visual examination of the site and adjacent areas.
Questions about the bidding documents must be submitted in writing, and questions received less than seven days prior to bid opening may not be answered. Questions received less than seven days prior to the date for opening of bids may not be answered.
Failure to submit required qualification information within the times indicated may disqualify a bidder from receiving an award. A bidders failure to submit required qualification information within the times indicated may disqualify bidder from receiving an award of the contract.