This is a sources sought notice for bank stabilization project in Chickasaw County, Mississippi. It is for planning purposes only and not a solicitation. The project involves earthwork, erosion control, and waterway construction. The notice outlines various contract requirements including commencement, prosecution, and completion of work, liquidated damages, correspondence, work to be performed by the contractor, physical data, payment for mobilization/demobilization, equipment schedules, variation in quantities, security requirements, and non-U. S. citizens working on contracts. It also details general contract requirements such as submittals, partnering, rights-of-way, contacting landowners, layout and marking, preconstruction conference, subcontracting plans, notification of area engineer, order of work, progress charts, payment invoices, insurance, work in quarantined areas, certificates of compliance, safety requirements, accident prevention, daily inspections, accident investigations, accommodations for government representatives, machinery and mechanized equipment, vehicle weight limitations, public utilities, damage to work, time extensions for weather, control of access, protection of existing stabilization work, surveys, and acceptance of completed work. Measurement and payment for job items like mobilization, clearing, grubbing, erosion control, environmental protection features, and excavation for grade control structures are also described.
The contractor shall complete the entire work ready for use not later than 180 calendar days after the date the contractor receives the notice to proceed.
Payment for mobilization and demobilization will be made in two installments: sixty percent upon completion of mobilization at the work site, and the remaining forty percent upon completion of demobilization.
If the contractor fails to complete the work within the time specified, the contractor shall pay liquidated damages to the government in the amount of $1,**** for each calendar day of delay.