USA | OH | LAKE COUNTY | MENTOR Small City
Verdantas - City Of Mentor - OH
Mentor - Blossom Drive Storm Sewer Replacement
Blossom Drive Storm Sewer Replacement Blossom Drive storm sewer replacement, including pavement repairs, sidewalk repairs, and drive apron replacements.
AI helper
The completion date is May 15, 2026. completion date: may 15, 2026
The contract award shall be based on the lowest and best bid or lowest responsive and responsible bid as applicable for the public contracting agency receiving bids for the base bid and selected alternate items if any for this project. he contract award shall be based on the lowest and best bid or lowest responsive and responsible bid as applicable for the public contracting agency receiving bids for the base bid and selected alternate items if any for this project.
The bidder shall provide detailed information relating to similar projects completed within the past 5 years which demonstrates the bidders capability, responsibility, experience, skill, and financial standing to undertake this type of project and shall include a list of all projects currently under construction including status and contact person. bidder shall provide detailed information relating to similar projects completed within the past 5 years which demonstrates the bidders capability, responsibility, experience, skill, and financial standing to undertake this type of project and shall include a list of all projects currently under construction including status and contact person.
The contractor shall pay to the owner as liquidated damages, an amount equal to liquidated, for each and every day sundays and legal holidays excepted the completion of the work may be delayed beyond the date fixed in the manner and as stipulated. further the contractor shall complete the whole of said work in accordance with the specifications and contract drawings to the satisfaction of the owner on or before the time stated, and in default of completion within the time as fixed, the contractor shall pay to the owner as liquidated damages, an amount equal to liquidated, for each and every day sundays and legal holidays excepted the completion of the work may be delayed beyond the date fixed in the manner and as stipulated.
Before submitting a bid, each bidder must visit the site to familiarize themselves with local conditions that may in any manner affect cost, progress, or performance of the work. before submitting a bid, each bidder must a. examine the contract documents thoroughly. b. visit the site to familiarize themselves with local conditions that may in any manner affect cost, progress, or performance of the work.
The opinion of probable construction cost is 220,**** of probable construction cost: 220, ****
Bid Close Date: