This bid notice is for a roofing project at Ranchero Middle School by the Hesperia Unified School District. The project involves roof replacement and rehabilitation across 13 different groups, with specific repair types detailed in accompanying maps. Bidders must submit itemized pricing for each group. A mandatory pre-bid job walk is scheduled for April 9, 2026. The bid deadline is April 17, 2026. Contractors must be prequalified through PQ Bids by April 12, 2026. The contract is for public works, requiring compliance with prevailing wage laws and DIR registration. The project is on an active campus, requiring contractors to minimize disruption. Liquidated damages apply for delays in submittals or project completion. The contract term is one year from the date of award, with potential extensions. Bid security is required in the form of a bid bond or cashier's check for at least 10% of the bid amount.
The bid deadline date is April 17, 2026, at 2:00 p. m.
The district will pay properly submitted vendor invoices within forty-five (45) days of receipt of goods or services, or a combination of both. Payment will not be made until goods or services are delivered, installed if required, and accepted as specified.
Contractor must provide a standard minimum two-year (2-year) contractor's workmanship warranty and the manufacturer's full system no dollar limit (NDL) warranty.
The district will determine the lowest responsive and responsible bidder based on the base bid amount plus whichever combination of additional roof groups the district chooses to fund at the time of award.
Contractors must be prequalified through PQ Bids. The last day to submit prequalification applications is April 7, 2026, at 5:00 p. m. The last day to be approved is April 12, 2026, at 5:00 p. m.
Liquidated damages are **** per day for each calendar date the start date is delayed if executed contract and required bonds/insurance are not received by the district prior to the scheduled start date. Liquidated damages are also **** per day for each calendar date completion is delayed if work is not ready for intended use within the specified time period.
A mandatory pre-bid job walk will be held on Thursday, April 9, 2026, at 7:00 a. m. at Ranchero Middle School.
The district has the discretion to request, and test, product samples prior to the award of the contract.
All inquiries, comments, or exceptions to the bid materials must be submitted in writing to ***@***. *. * no later than Friday, April 10, 2026, at 2:00 p. m.