RFB for synthetic turf replacement at three high school stadiums and track surface replacement with eight-lane expansion at Holt High School. Bids due December 9, 2026 at 2:00 PM CT via BidNet Direct. Optional site access available. Two bid paths: Path A (base system) and Path B (approved alternative systems). Award to lowest responsive and responsible bidder. Bid security 5% of maximum potential award. Liquidated damages $1,000 per calendar day per site. Substantial completion by July 2027. Prevailing wage applies. Performance and payment bonds required.
Substantial completion is required by July 30, 2027 for Holt and July 23, 2027 for Timberland and Liberty, with final completion by August 13, 2027. The notice to proceed is anticipated for January 4, 2027. Holt substantial completion july 30, 2027
Monthly itemized payment applications are submitted based on an approved schedule of values. The district may retain 5% of earned amounts. The district may retain five percent 5 of earned amounts or the maximum otherwise permitted by law.
A minimum eight-year, 100% non-prorated manufacturer system warranty is required for the turf, and a five-year contractor workmanship warranty. Provide a minimum eightyear, 100 nonprorated manufacturer system warranty covering carpet, fiber wear and loss, uv degradation, backing, tuft bind, seams, inlays, installed impact performance
Award will be made to the lowest responsive and responsible bidder or combination of bidders. award will be made to the lowest responsive and responsible bidder or combination of bidders for the complete site package or combination of site packages selected under this published method.
The prime contractor must have at least ten years of continuous experience in athletic surfacing construction. The prime contractor must have at least ten years of continuous experience in athletic surfacing construction and must satisfy the projectspecific qualifications in part 6.
Liquidated damages of $1,000 per calendar day per site apply after the applicable substantial completion date. liquidated damages 1, 000 per calendar day, per site, after the applicable substantial completion date
No prebid conference or site walk is mandatory, and attendance is not a condition of responsiveness. Optional site access may be requested. no prebid conference or site walk is mandatory, and attendance is not a condition of responsiveness.
Questions, approved equal requests, and alternative system requests are due by December 2, 2026 at 4:00 PM Central Time. questions approvedequal path b requests due wednesday, december 2, 2026 @4: 00 pm central time
Direct contact with board members, school staff, coaches, design consultants, or other district personnel regarding this procurement may result in disqualification. Direct contact with board members, school staff, coaches, design consultants, or other district personnel regarding this procurement may result in disqualification.