Sealed bids are sought for the installation of concrete pile caps, beams, and two recycle media filtration (RMF) treatment units adjacent to the wastewater treatment facility. Bids are due by 10:00 AM on Friday, July 24, 2026. Contractors must supply all materials and labor, and provide proof of general liability and workers' compensation insurance. The contract will be awarded to the lowest responsive and responsible bidder. Questions regarding specifications must be submitted in writing by 1:00 PM on Friday, July 17, 2026.
Bids must be received no later than 10:00 AM on Friday, July 24, 2026.
The town agrees to pay the contractor within thirty (30) days of receipt of an invoice detailing completed work and acceptance by the town.
The contractor guarantees that all labor furnished will be competent, the product of such labor will yield first-class results, materials and equipment will be of good quality and new, and the work will be of good quality, free from faults and defects.
The town will award the contract to the lowest responsive and responsible bidder.
Bidders must provide a minimum of three (3) references for whom they have completed contracts for work similar in size and scope within the last five (5) years.
The contractor will pay the town $1,000 per day for each calendar day of delay until the work is completed.
Failure to complete required forms, answer questions, or provide required documentation will result in the bid being deemed nonresponsive and rejected, unless determined to be a minor informality.