Demolition of existing structure, site work, repaving, fencing, security gates, jury boxes, and ballistic wall installation at Pahrump Justice Court. Mandatory prebid meeting on October 1, 2026. Bids due October 15, **** calendar days for completion. Liquidated damages $5,000 per day. Bid bond 10%, performance and payment bonds 100%. Prevailing wages required. Progress payments with 15% retention.
All work must be completed within 120 calendar days from the notice to proceed date. As stated: all work completed within one hundred and twenty 120 calendar days from the notice to proceed date.
Progress payments are made based on materials on site and labor expended. fifteen percent 15 of the amount ascertained will be deducted and retained by the county until after the completion of the entire contract in an acceptable manner and will be released thirty 30 days after the filing of the notice of completion.
Contractor must submit a contractor qualification form. The bidder must submit a contractor qualification a copy of which is included in this bid package for the bidder and any subcontractor the bidder intends to use for the job.
Liquidated damages of $5,000 per calendar day for late completion. the contractor may be liable for liquidated damages, payable to county in the amount of five thousand dollars 5, **** for each calendar day beyond the deadline taken for completion.
There will be a mandatory prebid meeting held on site. there will be a mandatory prebid meeting held on site thursday october 1, 2026 at 8: 00 a. m. , located at **** e. basin ave. , pahrump, nv ****.
All requests for information must be submitted by October 5, 2026. all requests for information must be submitted to the designated contact by october 5, 2026 to receive answers prior to bid opening.
Bids received after the deadline will not be honored. bids received after the deadline will not be honored, regardless of when postmarked or sent. Also, failure to submit required forms may disqualify the bid.