This is a public tender for a storm drain trash management plan, which includes the removal of existing storm drain pipes and the installation of trash management devices at a single location. The project is funded with local funds and has an engineer's estimate of $450,000. 00. The contract time for completion, excluding plant establishment and permanent erosion control, is 50 working days. A non-mandatory prebid outreach meeting is scheduled for March 26, 2026, at 2:00 p. m. in Chico, CA, with both in-person and Microsoft Teams options. Contract documents can be obtained from the Public Purchase online bidding service. Bidders must possess a Class A contractor license or a combination of classes required for the work. This contract is subject to state contract nondiscrimination and compliance requirements, as well as California prevailing wages. Contractors and subcontractors must be registered with the Department of Industrial Relations to bid on or perform public work. Payment retentions of 5% will be withheld from each progress payment, and securities may be substituted for these retentions. Questions and requests for information must be submitted through Public Purchase five business days prior to bid opening.
The bid notice states that the work, excluding plant establishment and permanent erosion control establishment work, must be completed within 50 working days. complete the work, excluding plant establishment and permanent erosion control establishment work, within 50 working days.
The bid notice specifies that five percent (5%) will be withheld from each progress payment made to the contractor for work performed and will be held until completion of the work, its acceptance, and the expiration of the period provided by law for filing liens by laborers or materialmen. In accordance with the provisions of section **** of the public contract code of the state of California, securities may be substituted for the monies which the city withholds, or the contractor may request that retention be paid to an escrow agent. Five percent 5 will be withheld from each progress payment made to the contractor for work performed and will be held until completion of the work, its acceptance and the expiration of the period provided by law for filing liens by laborers or materialmen. In accordance with the provisions of section **** of the public contract code of the state of California, securities may be substituted for the monies which the city withholds, or the contractor may request that retention be paid to an escrow agent.
The bid notice states that at the time the city awards the contract for this project, the contractor shall possess either a class a contractor license or a combination of classes required by the categories and types of work included in this contract. At the time the city awards the contract for this project, the contractor shall possess either a class a contractor license or a combination of classes required by the categories and types of work included in this contract.
The bid notice mentions a non-mandatory prebid outreach meeting scheduled for March 26, 2026, at 2:00 p. m. in the City of Chico Council Chambers Conference Room 1, 421 Main Street, Chico, CA 95928. The meeting will be in person with a Microsoft Teams option. A non mandatory prebid outreach meeting is scheduled for march 26, 2026 at 2: 00 p. m. in the city of chico council chambers conference room 1, 421 main street, chico, ca 95928. the meeting will be in person with a microsoft teams option.
The bid notice states that all questions and requests for information must be submitted five (5) business days prior to bid opening. Questions and requests for information must be submitted five 5 business days prior to bid opening.
The bid notice indicates that the engineer's estimate for this contract is $450,****. The engineer rsquos estimate for this contract is 450, ****.