The solicitation is for adding a UPS system to a server. Quotes are requested, and the deadline for submission is March 9, 2026, at 12 p. m. CT. A site visit is scheduled for February 23, 2026, at 10 a. m. MT. The estimated project magnitude is between $25,000 and $100,000. The contractor must commence work within five calendar days after receiving the notice to proceed and complete the work within 90 days after the notice to proceed. A payment bond will be required within 10 days of award. Questions must be submitted by March 4, 2026, at 12 p. m. CT.
The contractor must complete the entire work ready for use not later than 90 days after notice to proceed, which includes final cleanup of the premises. he contractor will be required to a commence work under this contract within five calendar days after the date the contractor receives the notice to proceed, b prosecute the work diligently, and c complete the entire work ready for use not later than 90 days after notice to proceed.
The government will pay the amount due the contractor after completion and acceptance of all work, presentation of a properly executed voucher, and presentation of release of all claims against the government. he government shall pay the amount due the contractor under this contract aftercompletion and acceptance of all workpresentation of a properly executed voucher andpresentation of release of all claims against the government arising by virtue of this contract, other than claims, in stated amounts, that the contractor has specifically excepted from the operation of the release.
Award will be made using the lowest price, technically acceptable approach. Award will be made using the lowest price, technically acceptable approach to source selection.
The responsible quoter must have the ability to comply with the required delivery or performance schedule, a satisfactory record of performance and integrity, a satisfactory safety and environmental record, satisfactory references, and the necessary facilities, equipment, materials, personnel, organization, experience, technical skills, and financial resources. A responsible quoter will: have the ability to comply with the required delivery or performance schedule, taking intoconsideration other business commitments. have a satisfactory record of performance and integrity. have a satisfactory safety and environmental record. have satisfactory references see past performance below. have the necessary facilities, equipment, materials, personnel, organization, experience, technical skills, and financial resources to fulfill the terms of the resultant contract.
A site visit is scheduled for February 23, 2026, at 10 a. m. MT. a site visit is scheduled for feb 23, 2026, at 10 a. m. mt.
Questions must be submitted to ***@***. *. * no later than March 4, 2026, at 12 p. m. ct. submit questions to ***@***. *. * no later than march 4, 2026, at 12 p. m. ct.
The estimated magnitude of this project is between $25,000 and $100,000. he estimated magnitude of this project is between 25, 000 and 100, 000.