Construction of expanded parking at Red Butte Garden including new parking areas, lighting, landscaping, shoring, and pedestrian connections. Mandatory pre-proposal meeting on October 8, 2026. Management plan and statement of qualifications due October 20, 2026. Bid bond of 5% required. Performance and payment bonds of 100% required. Completion by April 30, 2027 requested. Liquidated damages $1,000 per day. Value engineering proposals encouraged.
A completion date prior to April 30, 2027 is requested, but not mandatory. The actual notice to proceed will be based on how quickly the contractor returns the contract, bonds and other university requirements.
The selection of the prime contractor will be made using the VBS method. Points are awarded for cost (20 points), university past performance (50 points), strength of contractor's team (75 points), and project management approach (120 points).
The contractor shall comply with and require all of its subcontractors to comply with the license laws as required by the state of Utah. The contractor must submit a certification that neither it nor its principals are presently debarred, suspended, proposed for debarment, declared ineligible, or voluntarily excluded from soliciting work by any governmental department or agency.
Liquidated damages: $1,**** per day.
A mandatory pre-proposal meeting and site visit will be held at 1:00 pm on October 8, 2026 at Red Butte Garden. All prime contractors wishing to submit on this project must attend this meeting.
All requests for information regarding this project and questions must be submitted via the Bidnet Direct website no later than the time and date listed on the project schedule. The deadline for contractors to submit questions prior to submission of proposals is October 13, 2026 at 4:00 pm.
Late submittals and submittals that exceed the allotted page count will be considered nonresponsive and will be disqualified. Failure to attend the mandatory pre-proposal meeting precludes participation as a proposer. Incomplete reference information will result in a firm's disqualification from the selection process.
Construction cost is estimated at: $4,700,000.