Sealed bids for dune restoration at Pine Point Beach, including beach scraping and grass planting. Bids due Nov 23, 2026, 2:00 PM. Bid security of 5% required. Work substantially complete by Dec 31, 2026. Performance and payment bonds required. One-year warranty. Liquidated damages of $1,000/day for late substantial completion. No prebid conference. Questions via addenda. Award to lowest responsive bidder.
Work must be substantially complete by December 31, 2026. work associated with this agreement shall be substantially complete on or before december 31, 2026.
Progress payments made monthly, with 95% of completed work paid, retaining 5% until substantial completion, then 98% paid, with final 2% retained for one year. progress payments will be made in an amount equal to the percentage indicated below but, in each case, less the aggregate of payments previously made
Contractor must guarantee all materials, equipment, and work for one year from substantial completion. the contractor shall guarantee all materials and equipment furnished and work performed for a period of one year from the date of substantial completion.
Award to the responsible bidder submitting the lowest responsive bid. such award shall be to the responsible bidder submitting the lowest responsive bid.
Bidders must demonstrate qualifications, including financial data, previous experience, and authority to do business in Maine. bidder shall submit a written evidence establishing its qualifications such as financial data, previous experience, and present commitments
Liquidated damages of $1,000 per day for late substantial completion and $500 per day for late final completion. contractor shall pay owner 1, **** for each day that expires after the time. . . for substantial completion
Bidders must conduct a required site visit during normal working hours. bidder shall conduct the required site visit during normal working hours, and shall not disturb any ongoing operations at the site.
Questions about bidding documents must be submitted in writing, with addenda issued in response. questions received less than seven days prior to the date for opening of bids may not be answered.
Bids without security or completed certification forms will not be considered. bids submitted without bid security and completed certification forms will not be considered.