Sealed bids for construction of multiuse trail, fencing, landscaping, drainage and site improvements. Bid opening via Webex on December 2, 2026 at 11:00 AM. Bid bond 5% required. Performance and payment bonds 100% required. Maintenance bond 10% required. State funding of $554,**** with SBE and MBE goals. Completion within 210 days. Liquidated damages $1,800/day. Questions due November 20, 2026.
Work must be completed within 210 consecutive calendar days after award or notice to proceed. the date set for substantial completion for this project shall be within two hundred ten days 210 consecutive calendar days after the award of bid andor notice to proceed.
Payments are net 30 days from receipt and approval of progress payments. payment terms shall be net thirty 30 days from receipt and approval of each progress payments.
A maintenance bond is required for 12 months from final payment. the principal agrees to maintain the work completed in the contract, stated above, for a period of twelve 12 months from the date of final payment and without additional cost to the city.
The contract is awarded to the lowest responsible bidder. the contract will be awarded by the owner to the lowest responsible bidder and the lowest responsible bid shall be determined based upon the sum of the base bid and bid alternates selected.
Bidders must have been regularly engaged in this type of work for at least 5 years. the bidder has been regularly engaged in the type of work set forth in the contract documents for a period of not less than five 5 years prior to the bid date.
Liquidated damages of $1,800 per day for delay. bidder shall pay the city one thousand eight hundred dollars 1, **** for each day that expires after the time specified in this section for substantial completion.
Each bidder shall visit and examine the site. each bidder shall visit and examine the site of the proposed work and fully acquaint himself with conditions.
Questions must be submitted in writing by November 20, 2026. deadline for submission of questions is friday, november 20, 2026, noon est.
Bids received after the time set for opening will not be considered. bids and amendments to bids received after the time set for the bid opening will not be considered.
There is $554,**** in state funding for this project. there is 554, **** in statefunding for this project.