Renovation of five public restrooms at Aransas Pass Civic Center. Proposals due 11/19/2026, 3:00 PM local time. Two sealed hard copies required; electronic submissions not accepted. Non-mandatory site visit on 11/09/2026. Proposal bond of 5% required. Performance and payment bonds of 100% required. Evaluation based on price (40%), experience (20%), approach (20%), schedule (10%), team (10%). Existing floor tile must be retained and protected. Standard commercial non-illuminated mirrors required. No liquidated damages. City budget is $200,000.
Proposals are due by 3:00 p. m. local time on Thursday, November 19, 2026. The document states: proposals due 3: 00 p. m. local time, thursday, november 19, 2026.
The contractor must provide a correction period of at least one year. The document states: provide a correction period of not less than one 1 year from the date of substantial completion.
The award is based on best value with specific criteria. The document states: award, if made, will be to the responsible proposer whose proposal is determined by the city to provide the best value to the city.
Proposers must demonstrate experience in comparable projects. The document states: comparable occupied municipal, civic, institutional, or commercial restroom renovations and plumbing and electrical work shall be performed by trades licensed in the state of texas.
A non-mandatory site visit is scheduled. The document states: a nonmandatory site visit will be held at the aransas pass civic center on monday, november 9, 2026, between 8: 00 a. m. and 3: 00 p. m. .
Written questions are due seven days before the proposal deadline. The document states: written questions are due seven calendar days before the proposal deadline and written questions due 3: 00 p. m. , thursday, november 12, 2026.
Unauthorized contact with city officials may lead to disqualification. The document states: contact with other city officials, employees, or the design representative regarding this procurement may be grounds for disqualification.
The city's approved construction budget is $200,000. The document states: the citys approved construction budget for this project is 200, 000.