Replace two two-ton monorail cranes with a single two-ton underhung class C hand geared bridge crane at Rancho Penasquitos facility. Bids due November 5, 2026, 2:00 PM via BidNet Direct. Prebid meeting and optional site visit on October 15, 2026. Bid guarantee of 10% required. Class A or **** contractor license required. DIR registration mandatory. Prevailing wages apply. Completion by March 15, 2027. Questions due October 27, 2026.
Complete all work by March 15, 2027. the contractor shall complete the work by the completion date of march 15, 2027.
Monthly progress payments: the water authority shall pay contractor, within 30 days of receipt of the invoice, 95 percent of the invoice amount.
Lowest, responsible, and responsive bidder. make an award to the lowest, responsible, and responsive bidder as the interest of the water authority may require.
Requires Class A general engineering or **** machinery and pumps contractor license, and DIR registration. contractor shall possess a valid class a general engineering contractor license or class **** machinery and pumps contractor license.
Forfeit up to $200 per day per worker for underpayment of prevailing wages. forfeit not more than two hundred dollars 200 for each calendar day. . . for each worker paid less than the prevailing wage rates.
Optional site visit on October 15, 2026, after prebid meeting. a site visit will be conducted at the rancho penasquitos pressure control and hydroelectric facility site. . . immediately following the prebid meeting on october 15, 2026.
Questions due by 5:00 PM on October 27, 2026. no later than 5: 00 p. m. on october 27, 2026, to mike vanoli, management analyst, at mvanoli@sdcwa. org.
Bids without required bid guarantee or DIR registration are nonresponsive. a bid that is not accompanied by a bid guarantee is nonresponsive. bids from contractors or subcontractors that are not registered as required will be deemed nonresponsive.