UMBC seeks a third-party solar provider for a 25-year PPA to design, install, own, operate, maintain, and finance ~1 MW solar PV systems (warehouse rooftop and North Stadium Lot carports). Mandatory preproposal conference and site visit on December 4, 2026. Proposals due January 15, 2027. MBE subcontracting goal of 10%. UMBC will provide up to $750,000 as a one-time lump-sum payment. Performance bond required. Insurance requirements specified. Proposals irrevocable for 120 days. Award based on technical and financial merit, equally important.
Construction completion date is March 31, 2028, desired substantial completion. Offerors will not be penalized for a schedule shown past this date. construction completion date: march 31, 2028 desired substantial completion
UMBC will provide 600kWdc up to $750,000 total as a one-time lump-sum payment at initiation of work, released upon approval of construction documents. umbc will provide 600kwdc up to 750, 000 total as a onetime lumpsum payment at the initiation of work
A 25-year roof penetration and building penetration warranty is required. 25year roof penetration and building penetration warranty
Technical and financial merit shall be equally important. Award to the responsible offeror whose proposal is most advantageous to the university. technical and financial merit shall be equally important
Offeror must have at least 5 years experience and provide at least 3 references from organizations of similar size and scope. the offeror shall have at least 5 years experience providing the requested services
Liquidated damages apply for MBE non-compliance, e. g. , **** per day for late monthly reports. failure to submit each monthly payment **** per day
Mandatory in-person preproposal conference and site visit on December 4, 2026, at UMBC Facilities Management building. mandatory inperson preproposal december 4, 2026, at 1: 00 pm est
Questions due December 18, 2026, at 10:00 AM EST. questions due date time: december 18, 2026, at 10: 00 am est
Late proposals will not be considered. Attempts to contact evaluation committee members may be grounds for disqualification. late proposals. . . will not be considered