Public works project to replace two HVAC units at Visalia Water Reclamation Facility. Mandatory prebid meetings on October 19 and 21, 2026. Bid deadline November 5, 2026 at 2:30 PM. Requires C20 license, DIR registration, prevailing wages. Bid security 10% required. Completion within 60 calendar days of notice to proceed. Payment and performance bonds 100% each. One-year warranty on labor and materials. Liquidated damages $200 per day. Budget estimate $85,000.
The project must be completed within 60 calendar days from the notice to proceed. the entire project must be completed within sixty 60 calendar days from the effective date of the notice to proceed.
Payment terms are not explicitly detailed in the document beyond standard public works procedures. No specific payment schedule is provided.
The contractor shall provide a minimum one-year warranty on all labor, installation work, and materials. the contractor shall provide a minimum oneyear warranty on all labor, installation work, and materials furnished for the replacement of the hvac units.
Award is made to the lowest responsive and responsible bidder. award shall be made to the lowest bidder whose bid is deemed both responsive and responsible and meets the criteria and specifications set forth in this rfb.
Contractor must hold a valid C20 warm-air heating, ventilating and air-conditioning contractor license. holds a valid c20 warmair heating, ventilating and airconditioning contractor license.
Liquidated damages of $200 per calendar day for delay. bidder shall pay the city liquidated damages in the amount of two hundred dollars 200 a day for each calendar day the project is delayed beyond the time of completion date.
Mandatory prebid meetings are required. bidder is required to attend at least one of the mandatory prebid meetings in order to be eligible to submit a bid.
Protests must be filed within 5 working days after the bidder knows of the facts. may protest to the city of visalia purchasing division in writing within five 5 working days after such aggrieved bidder knows, should have reasonably known, or could reasonably be expected to know of the facts giving rise thereto.
Bids received after the deadline will be rejected. bids received after the bid deadline will be rejected. Also, failure to attend mandatory prebid meeting disqualifies bidder.
The budget estimate is approximately $85,000. budget estimate for this project is approximately 85, 000.