USA | IL | KANE COUNTY | GENEVA | 60134 Small City
City Of Geneva - IL
Wastewater Treatment Equipment/ Water Purification Equipment/ Mechanical Equipment/ Industrial Machinery Manufacturing/ Equipment Suppliers
Wastewater Plant Grit Classifier Replacement
Wastewater Plant Grit Classifier Replacement Removal of existing grit classifier and installation of a new grit classifier.
AI helper
The project requires substantial completion within thirty (30) calendar days of the new grit classifier's availability, with final completion following an additional thirty (30) days. The contractor agrees to perform all of the work described in the contract documents and comply with the terms therein for the sum of , as shown in the bid form section ****.
Contractor warrants that its work shall be free from defects and shall be suitable for the use intended. In the event that any deficiencies in the contractors work are discovered within one year after completion of the project, contractor shall, at its sole cost, repair or replace any defective work. Contractor warrants that its work shall be free from defects and shall be suitable for the use intended.
The contract will be awarded to the lowest responsive, responsible, and eligible bidder. The contract will be awarded to the lowest responsive, responsible, and eligible bidder.
To demonstrate qualifications, bidders must be prepared to submit detailed written evidence such as financial data, previous experience, and present commitments within five days after bid opening upon owner's request. To demonstrate qualifications to perform the work, each bidder must be prepared to submit within five days after bid opening, upon owners request, detailed written evidence such as financial data, previous experience, present commitments, and other such data as may be called for.
Liquidated damages for substantial completion are $1,**** per day, and for final completion, **** per day. Liquidated damages shall commence, and contractor shall pay owner, one thousand dollars $1,**** for each day that expires after the time specified for substantial completion until the work is fully operational and tested.
Before submitting a bid, each bidder must visit the project sites to become familiar with local conditions. Before submitting a bid, each bidder must a examine the contract documents, including addenda, thoroughly, b visit the project sites to become familiar with local conditions that may in any manner affect cost, progress or performance of the work
A bid may be rejected if the bidder is not properly qualified or if the bid is unbalanced. Failure to execute the agreement and furnish required bonds and insurance within ten days of the notice of award can lead to forfeiture of the bid bond. Owner also reserves the right to reject the bid of any bidder that owner considers to be unqualified relative to article 1 above.
Bid Close Date: