The contract is for the construction of a new precast concrete building and modification of the existing digester building, including the installation of a new heat exchanger boiler unit. Bids are on a unit price basis. The submission deadline is September 3, 2026, at 2:00 PM EST. The entire project is under a single prime contractor. Liquidated damages apply for delays after substantial and final completion.
Liquidated damages are $1,500 for each day after substantial completion and $500 for each day after final completion. 1, 500 for each day after substantial completion ii. 500 for each day after final completion
A site visit was held on August 26, 2026, at WWTF, **** Crab Creek Road, Christiansburg, Virginia. site visit: wwtf, **** crab creek road, christiansburg, virginia
Questions were due by 5:00 PM on August 18, 2026. all questions are to be submitted to jennifer miller cha, at ***@***. *. * no later than 5 pm, local prevailing time, august 18
Bidders must provide certifications regarding debarment, workers compensation, noncollusion, and EEO compliance. contractors policy of nondiscrimination section ****, and contractors policy of drugfree workplace section ****
Bids will be received at the finance office until 2:00 pm on August 27, 2026, or via electronic submission on EVA. bids will be received at the finance office until 2: 00 pm on august 27, 2026, at 100 east main street christiansburg, va **** or via electronic submission on eva.