RFP for CM/GC services to design and construct two new elevator towers with four elevators and lobby renovations at Rice-Eccles Stadium West Tower. Fixed contract price limit is $16,575,500. Mandatory preproposal meeting on October 8, 2026 at 1:00 PM. Proposals due October 16, 2026 by 2:00 PM via Bidnet Direct. Must be Utah licensed general contractor. Bid bond of 5% of fixed contract price limit required. Target substantial completion by August 27, 2027. Existing elevators must remain operational. ADA access must be maintained. Liquidated damages of $2,000 per day for late completion.
Target project substantial completion is August 27, 2027. The RFP states: target project substantial completion august 27th, 2027 date.
The selection uses value based selection with criteria including past performance, qualifications, management approach, and cost proposal. The RFP states: the contractor that is ranked the highest will represent the best value for the state.
Contractor must be a Utah licensed general contractor. The RFP states: the contractor for the project must be a utah licensed general contractor.
Liquidated damages of $2,000 per day for late completion. The RFP states: agree to pay liquidated damages in the amount of 2, **** per day for each day after expiration of the contract time that the work is not substantially complete.
Questions must be submitted by October 12, 2026. The RFP states: deadline for contractors to submit questions prior to submission of proposals monday, october 12th, 2026 4: 00pm.
Failure to attend mandatory preproposal meeting, late proposals, missing bid bond, or exceeding page limits can cause disqualification. The RFP states: a contractors absence from the mandatory preproposal meeting or failure to sign the meeting attendance log precludes participation as a proposer on this project.
The fixed contract price limit is $16,575,500. The RFP states: the fixed contract price limit, as defined in the cmgc agreement, is: 16, 575, ****.