USA | IL | COOK COUNTY | HOFFMAN ESTATES | 60169 Small City
He Parks - Hoffman Estates Park District - IL
Utilities for Birch Park
Utilities installation at Birch Park Installation of all proposed onsite utilities including storm sewer improvements and dewatering, removal of trench spoils, soil testing
AI helper
Work must be substantially completed by June 15, 2021, with final completion by July 1, 2021. The document states: substantial completion completion date: july 1, 2021.
Monthly estimates may be presented no later than the first Monday of each month, with payments made within approximately 30 days after review. The document states: payments will be made within approximately thirty 30 days after review by the owner.
The contractor must provide a minimum one-year warranty for all materials and workmanship. The document states: the contractor andor manufacturer shall provide a minimum of one 1 year warranty for all materials and workmanship.
The contract will be awarded to the lowest responsible bidder. The document states: award of contract will be made to the lowest responsible bidder, as determined by the board of commissioners.
Bidders must submit at least five references for similar projects completed within the past two years. The document states: please submit at least five 5 references for similar projects completed within the past two 2 years.
Failure to comply with contract conditions may result in termination for default, and the contractor may be liable for excess costs. The document states: failure to comply with the conditions set forth in the contract documents shall result in the termination of the contract for default.
Bidders are encouraged to visit the site to verify conditions. The document states: bidders should visit the site and take such other steps as may be reasonably necessary to ascertain the nature and location of the work.
Failure to provide required bid guarantee, bonds, or complete required forms may cause rejection. The document states: failure to furnish a bid guarantee in the proper form and amount by the time set for opening of bids may be cause for rejection of the bid.