USA | OH | ROSS COUNTY | FRANKFORT Small City
Verdantas - Village Of Frankfort - OH
Frankfort - Sanitary Sewer Rehabilitation
AI helper
The work will be substantially completed on or before 120 days after notice to proceed, and completed and ready for final payment on or before 150 days after the notice to proceed. the work will be substantially completed on or before 120 after the notice to proceed
Progress payments are made based on applications, with 8% retainage until 50% completion, then paid in full. owner will retain an amount equal to 8 of each progress payment application until 50 of the work has been completed
The contract will be awarded to the responsive and responsible bidder with the lowest bid. it will be awarded to the responsive and responsible bidder with the lowest bid
Bidders must submit written evidence of financial data, previous experience, and present commitments within five days of owner's request. bidder shall submit written evidence such as financial data, previous experience, present commitments
Liquidated damages for delay are specified in the agreement, ranging from $500 to $2,000 per calendar day depending on contract amount. contractor shall pay owner the following daily charge: original contract amount daily charge
Questions about the meaning of bidding documents must be submitted in writing, and questions received less than ten days before bid opening may not be answered. Questions received less than ten days prior to the date for opening of bids may not be answered
Bids may be rejected if nonresponsive, incomplete, nonconforming, unbalanced, obscure, or conditional. owner reserves the right to reject any or all bids, to waive any and all informalities
The opinion of probable construction cost is $586,300. opinion of probable construction cost: 586, 300
Bid Close Date: