RFP for painting, caulking, priming, and pressure washing at Carrington Place Apartments. Mandatory site walkthrough on 12/17/2026 at 3 PM EST. Pre-proposal meeting on 12/07/2026 via Teams. Proposals due 12/29/2026. Two-step bidding process. Bid bond required if bid exceeds $100,000. Performance and payment bonds required. Davis-Bacon wage rates apply. 10% retainage on payments. 180 days to complete project. Liquidated damages of $150 per day for schedule delays. 365-day warranty required. Award based on lowest responsive responsible bidder with evaluation points.
Proposals must be submitted by 12/29/2026. The contractor has up to 180 days to complete the project after notice to proceed. the contractor shall have up to 180 days to complete the project after the notice to proceed.
Progress payments are made at 30-day intervals based on percentage of work completed, with 10% retainage held on each payment. progress payments for acceptable work and materials delivered and stored on the site will be made at 30day intervals.
All work must be warranted for at least 365 days. all work provided by any contractor pursuant to any contract that ensues from this rfp shall be warranted or guaranteed by that contractor for a period of time of not less than 365 days.
The contract is awarded to the lowest responsive responsible bidder, with evaluation points for cost, technical understanding, approach, capabilities, experience, and quality. the agency intends to retain a contractor pursuant to a low bid basis, also taking into consideration responsiveness and responsibility.
Bidders must be qualified, licensed, experienced, and insured. They must submit licenses, a profile of firm form, managerial and financial capacity description, and client references. soliciting bids from qualified, licensed, experienced and insured independent contractors.
Liquidated damages of $150 per day are charged if the contractor fails to maintain the construction schedule. he/she will be charged with liquidated damages of 150 per day.
A mandatory site walkthrough is scheduled for 12/17/2026 at 3 PM EST. mandatory site walkthrough site walkthorugh **** from 3 pm est
Written inquiries must be submitted by 12/18/2026. written inquiries submittal deadline ****
Bids received after the deadline will not be accepted. Bids without a required bid bond will be rejected as nonresponsive. Additional marks or notations on documents may invalidate the bid. bids received after the published deadline will not be accepted.