RFP for commercial kitchen equipment project at U. S. Bank Stadium. Scope includes furnishing and installing kitchen equipment, removal of existing equipment, utility connections, testing, and commissioning. Mandatory site visit on October 28, 2026. Proposals due November 9, 2026, 4:00 PM CT. Two-year warranty required. Performance and payment bonds required at 100% of proposal cost. Prevailing wages apply. Project must be completed by February 26, 2027. Evaluation based on project delivery, technical approach, commercial terms, and interview.
The project must be completed by February 26, 2027. The RFP states: The project must be completed by february 26, 2027 the required completion date.
Payments are made based on approved applications. The authority shall make payment not later than 45 days after approval. 5% retainage is held until final payment. The RFP states: the authority shall make payment of the approved amount to the trade contractor not later than fortyfive 45 days after the authority has approved application for payment.
A two-year onsite warranty is required. The RFP states: twoyear onsite warranty to repair or replace the work and services constituting the project.
The authority will select the proposer whose final proposal is most advantageous and the best value. The RFP states: the authority will select in its discretion the proposer whose final proposal is most advantageous and the best value to the authority.
Proposers must have significant experience in design and construction similar to the project. The RFP states: proposers should have significant experience in design and construction similar to the project that is the subject of this rfp.
Failure to comply with prevailing wage requirements may result in civil or criminal penalties. The RFP states: failure to comply with the aforementioned may result in civil or criminal penalties.
A site visit is mandatory prior to submitting a proposal. The RFP states: a site visit is mandatory prior to submitting a proposal.
Written questions are due October 30, 2026, 4:00 PM. The RFP states: written questions due october 30, 2026, 4: 00 p. m.
Proposers who fail any pass/fail criterion may have their proposal rejected. The RFP states: proposers who fail any criterion may have their proposal rejected.