The bid is for the nb boone bridge i5 over willamette river at mp **** joint rehabilitation project. Bids must be submitted through the oregonbuys system. The project start date is upon issuance of notice to proceed, with substantial completion by september 24, 2026, and final completion by october 8, 2026. The deadline for solicitation protests, requests for change, requests for clarification, requests for approval of equivalents, and questions is 7 calendar days prior to the bid opening date. The public opening will occur immediately following the closing/bid opening date. Award protest deadline is 5 calendar days after issuance of the notice of intent to award. The project estimate for bonding purposes is between $2,000,000 to $2,500,000. Liquidated damages will apply for failure to complete the project by the substantial completion date and for lane closures beyond the allowed limits. This itb and any resulting contract are subject to the state buy america requirements, pursuant to ors 279c. 303. The state is committed to taking active steps toward increasing and promoting diversity, equity, and inclusion values across procurement processes for minorityowned, womenowned, emerging small, and veteranowned businesses by reducing barriers to compete for and be awarded state contracts.
The project has a substantial completion date of september 24, 2026 and a final completion date of october 8, 2026.
Award will be made to the responsible bidder submitting the lowest responsive bid.
Bidder must be registered in oregonbuys to do business with the state.
Liquidated damages will apply to the contract resulting from this itb for failure to complete the project by the substantial completion date, and for lane closures beyond the allowed limits.
Site access prior to closing will not be provided.
The deadline for solicitation protests, requests for change, requests for clarification, requests for approval of equivalents, and questions is 7 calendar days prior to the bid opening date identified in oregonbuys for this itb.
The project estimate for bonding purposes is 2, 000, 000 to 2, 500, 000.