USA | OH | LORDSTOWN
Verdantas - Village Of Lordstown - OH
Lordstown - Salt Springs Road SR45 Water Booster Station Upgrade
AI helper
The completion date for the project is September 25, 2026.
The bid notice does not explicitly state payment terms, but refers to progress payments as outlined in Article 14 of the General Conditions.
The correction period for defective work is two years after final acceptance of the entire project and final payment by the owner.
The contract award shall be based on the lowest and best bid or lowest responsive and responsible bid.
Bidders shall provide detailed information relating to similar projects completed within the past 5 years which demonstrates the bidders capability, responsibility, experience, skill, and financial standing.
Failure to complete the work within the time fixed will result in the contractor paying liquidated damages for each and every day the completion is delayed beyond the date fixed.
Bidders are required to visit the site to familiarize themselves with local conditions that may affect the cost, progress, or performance of the work.
Contractors shall submit samples as specified in the specifications, clearly identifying each sample with pertinent data.
The bid notice does not specify a challenge deadline for the bid itself, but claims related to the contract must be submitted to the engineer within 30 days of the event giving rise thereto.
The opinion of probable construction cost is $612,****.
Bid Close Date: