Mariposa County Sheriff's Office seeks proposals for extending security fencing, adding asphalt parking area with drainage curb, and relocating lighting at the Adult Detention Facility. Project budget not to exceed $75,000. Site visit recommended on November 17, 2026. Questions due November 20, 2026. Proposals due November 30, 2026. California public works project requiring prevailing wages and DIR registration. Payment bond required for contracts over $25,000. One-year workmanship warranty required. Evaluation based on completeness, experience, approach, and pricing/value.
Proposals must be received no later than November 30, 2026, at 4:00 p. m. The RFP states: All proposals must be received no later than november 30, 2026, at 4: 00 p. m.
Progress payments may be based on mobilization, completed fencing, completed grading, completed asphalt paving, and final completion. The RFP states: progress payments may be based upon: mobilization. completed fencing. completed grading. completed asphalt paving final completion and deficiency list.
Contractor shall provide a minimum one-year workmanship warranty. The RFP states: Contractor shall provide a minimum oneyear workmanship warranty beginning upon substantial completion.
Proposals evaluated on completeness, experience, approach, and pricing. The RFP states: pricing, cost savings, and overall value within the 75, 000 allinclusive project ceiling. overall value to the owner. 35
Contractor must be registered with DIR and provide license number. The RFP states: The contractor and subcontractors must be currently registered with dir as required by labor code **** and ****.
A preproposal site visit is strongly recommended. The RFP states: the preproposal site visit is scheduled for november 17th, 2026, at 10: 00 a. m.
Protests must be submitted within five days after notice of intended award. The RFP states: Any protest must be submitted within five 5 days after the notice of intended award is provided by email or mail to proposers.
Proposals must include required documentation and comply with all requirements. The RFP states: any item not expressly identified as an exclusion shall be assumed to be included if reasonably necessary to provide a complete installation.
The project budget is not to exceed $75,000. The RFP states: project budget not to exceed 75, 000. the total county cost for the entire project, including all work, materials, taxes, bonds, permits, contingencies, and any change orders, shall not exceed 75, 000.