The project is the renovation of fire station 17 to create a bunker gear room and improve the vestibule. Work includes demolition, new partitions, finishes, and MEP work. The estimated cost ranges from $267,**** to $356,**** mandatory prebid site visit is scheduled for September 24, 2026, at 11:00 am MT. The bid submission deadline is October 8, 2026, at 2:00 pm MT via BidNet. The contract time is 120 calendar days plus 10 days for mobilization. Liquidated damages are $1,**** per day for delays. A minimum of 80% Colorado labor is mandated.
The city shall make progress payments on account of the contract price on or about thirty days after the submission by the contractor to the city of a proper application for payment. on or about thirty 30 days after the submission by the contractor to the city of a proper application for payment.
Warranties required by the contract documents shall commence on the date of substantial completion unless otherwise provided in the notice of substantial completion. warranties required by the contract documents shall commence on the date of substantialcompletion unless otherwise provided in the notice of substantial completion.
The intent of the city is to award a contract to the lowest responsible bidder provided the bid has been submitted in accordance with the requirements of the bidding documents, is judged to be fair and reasonable, and to be in the best interest of the city. it is the intent of the city to award a contract to the lowest responsible bidder provided the bid has been submitted in accordance with the requirements of the bidding documents, is judged to be fair and reasonable, and to be in the best interest of the city.
Bidders may be required to submit a statement of qualifications including work performed in the last five years, plant, equipment, and recent CPA certified financial statements. the statement of qualifications shall include, at a minimum, the following information: a. work performed by the bidder in the last five years, including names, addresses and telephone numbers of references and dollar value of projects
As liquidated damages for delay, the contractor shall pay the city $1,**** for each calendar day that expires after the time specified. contractor shall pay city one thousand and no 100 dollars 1, **** for each calendar day that expires after the time specified in paragraph 5. 02 a and b above until the completion dates are satisfied.
A mandatory prebid site visit is scheduled for September 24, 2026, at 11:00 am MT at the Aurora Fire Rescue Station 17. prebid site visit mandatory september 24, 2026 @11: 00am mt
Written questions must be submitted by September 29, 2026, at 3:00 pm MT. written questions deadline september 29, ****: 00 pm mt
Failure to monitor BidNet for addenda may lead to reliance on incomplete information, subjecting bids to automatic disqualification. failure to do so may lead to reliance on incomplete, inaccurate, or out of date information when submitting bids subjecting such bids to automatic disqualificationfrom consideration.
The estimated cost for this project ranges from $267,**** to $356,****. the estimated cost for this project ranges from 267, **** to 356, ****.