Construction project to replace an existing two-bay, stopboard, weir structure in Parker Creek. The project involves removal of the old structure and construction of a new reinforced concrete structure. The period of performance is 62 calendar days, anticipated from August 31, 2026, to October 30, 2026. Contractors must be experienced in concrete water control structures. A site visit is strongly encouraged. The acquisition is a total small business set aside. Performance and payment bonds will be required.
The period of performance shall be 62 calendar days and will commence upon issuance of the notice to proceed (NTP). The anticipated period of performance is August 31, 2026 - October 30, 2026. The anticipated period of performance is August 31, 2026 October 30, 2026.
The contract award will be made on the basis of technical approach, past performance, and price. The basis of contract shall be on technical approach, past performance, and price, as acceptability for this requirement below.
Contractor shall be experienced and have demonstrated positive past performance with the design and construction of various concrete, pour-in-place water control structures. Contractor shall be experienced and have demonstrated positive past performance with the design and construction of various concrete, pour-inplace water control structures.
Offerors are strongly encouraged to attend the scheduled site visit to gain a comprehensive understanding of the project location and site conditions. Offeror s are strongly encouraged to attend the scheduled site visit to gain a comprehensive understanding of the project location and site conditions.
Failure to provide required bonds may result in contract termination for default. Failure to provide required bonds may result in contract termination for default.
The construction magnitude is estimated to be between $50,**** to $60,****. The construction magnitude is estimated to be between 50,**** to 60,****.