City of Charlotte, MI seeks sealed bids for construction of a recycling storage and processing building expansion (EGLE project ****). Bidders may bid Package A (building and site improvements), Package B (HMA improvements), or both. Non-mandatory prebid meeting and site walk on November 24, 2026 at 1:00 PM at 201 Hall Street, Charlotte, MI. Written questions due December 1, 2026. Bids due December 8, 2026 at 10:00 AM at City Clerk's Office. Performance and payment bonds required for contracts over $50,000. Substantial completion within 60 days after notice to proceed. Liquidated damages $100/day for delay. One-year warranty on workmanship and materials. Insurance requirements include CGL, auto, workers comp, and professional liability.
Substantial completion required within 60 days after notice to proceed. The work will be substantially complete within 60 days after the date when the contract times commence to run as provided only after written notice to proceed.
Progress payments for satisfactorily completed work, final payment after completion and acceptance. Contractor may submit itemized progress payment applications for satisfactorily completed work, subject to city verification.
One-year warranty against defects in materials and workmanship. Contractor warrants work against defects in materials and workmanship for one year after written final acceptance.
Lowest responsive and responsible bid. Awards may be made for package a, package b, both to one bidder, or separately to different bidders, based on the lowest responsive and responsible bid.
Contractor must be licensed in Michigan and in good standing. The selected contractor must be licensed in the state of michigan, in good standing, and able and qualified to perform service under this rfp.
Liquidated damages of $100 per day for delay. Contractor shall pay city **** for each day that expires after the time as duly adjusted pursuant to the contract specified above for substantial completion.
Non-mandatory prebid meeting and site walk. A nonmandatory prebid meeting and site walk will be held at cara 201 hall street, charlotte, mi on tuesday, november 24 at 1:00pm.
Written questions due December 1, 2026 at 1:00 PM. Written questions are due tuesday, december 1, 2026 at 1:00pm.
Bids must be sealed and received by deadline; work before insurance certificate may not be compensable. Any work performed proir to presentment of an acceptable insurance certificate may not be compensable.