Sealed bids for roadway resurfacing project in McDonough, GA. Includes traffic control, asphalt milling, paving, striping, and signage. Nonmandatory prebid conference on Oct 16, 2026. Questions due Oct 23, 2026. Bids due Nov 6, 2026, at 2:00 PM. Bid security 5% of max bid. Performance and payment bonds 100% each. Substantial completion in 75 days, final in 90 days. Liquidated damages $250/day after substantial completion, $500/day after final. Unit price basis. Contingency allowance $175,000. GDOT prequalification required.
Work must be substantially complete within 75 calendar days and completed and ready for final payment within 90 calendar days after contract times commence. the work will be substantially complete within 75 calendar days after the date when the contract times commence to run
Progress payments made on or about the 25th of each month, 95% of work completed and stored materials, with balance as retainage. progress payments will be made in an amount equal to the percentage indicated below but, in each case, less the aggregate of payments previously made
Contract awarded to the bidder whose bid is in the best interests of the owner. owner will award the contract to the bidder whose bid is in the best interests of the owner
Bidders must submit a current Georgia Department of Transportation prequalification certificate for roadway construction. required bidder current georgia department of transportation prequalification certificate for roadway construction
Liquidated damages of $250 per day after substantial completion deadline, and $500 per day after final completion deadline. contractor shall pay owner 250 for each day that expires after the time specified in paragraph 4. 02 above for substantial completion
Bids may be rejected if nonconforming, nonresponsive, unbalanced, or conditional. owner reserves the right to reject any or all bids, including without limitation, nonconforming, nonresponsive, unbalanced, or conditional bids