City of Aurora seeks bids for Triple Creek Trailhead Phase 2 improvements, including site work, discovery area, and mountain bike skills course. Estimated cost ranges from $937,**** to $1,036,**** must be completed within 120 consecutive calendar days plus 10 days for mobilization after notice to proceed. Liquidated damages are **** per day. Bids due December 2, 2026, via Bidnet. Bid bond of 5% required. Optional prebid call on November 13, 2026. Written questions due November 19, 2026. Award to lowest responsible bidder. SBE program applies for contracts over $250,000.
The work must be completed within 120 consecutive calendar days plus 10 days for mobilization after the notice to proceed. The document states: the contract time for completion of the work on this project shall be completed within 120 consecutive calendar days plus 10 consecutive calendar days for mobilization.
Progress payments are made on the basis of applications for payment, with 95% of work completed paid and 5% retainage withheld. The document states: ninetyfive 95 percent of work completed with the balance being retainage.
The contract will be awarded to the lowest responsible bidder. The document states: it is the intent of the city to award a contract to the lowest responsible bidder provided the bid has been submitted in accordance with the requirements of the bidding documents.
Bidders may be required to submit a statement of qualifications. The document states: bidders may be required, either before or after the bid opening, to submit a statement of qualifications to the project manager.
Liquidated damages of **** per day apply for delays. The document states: contractor shall pay city two hundred and no100 dollars **** for each calendar day that expires after the times specified.
Written questions must be submitted by November 19, 2026. The document states: written questions deadline november 19, ****: 00 pm mt.
Bids not submitted through Bidnet by the deadline will be rejected. The document states: bids received using another method such as mail, email, or hand delivery will not be accepted. late bids will not be accepted.
The estimated cost ranges from $937,**** to $1,036,****. The document states: the estimated cost for this project ranges from 937, **** to 1, 036, ****.