The project involves roof improvements at multiple locations in Leon County, Texas. The work includes repairs to a single-ply PVC membrane, installation of a metal over metal recover system, and other related tasks. The contractor is required to provide a two-year warranty for materials and installation, as well as manufacturers' guarantees. The bid must be submitted in complete original form by mail or messenger to the Leon County Auditors Office. The work schedule is between 7:00 am and 6:00 pm, Monday through Friday, excluding holidays. Weekend work is permitted only after owner prior approval.
The contractor agrees that work will be continuous and substantially complete within fortyfive 45 calendar days after the notice to proceed. bidder agrees that work will be continuous and substantially complete within fortyfive 45 calendar days after the notice to proceed.
Payment shall be made in monthly progress payments based upon applications for payment pay applications submitted by contractor to roof consultant for review and certifica tion. Payment shall be made in monthly progress payments based upon applications for payment pay applications submitted by contractor to roof consultant for review and certifica tion.
The contractor is responsible for repairing any defect attributable to contractors method or manner of installation of the roof membrane during the twoyear period at contractors sole cost and expense. he contractor shall be responsible for repairing any defect attributable to contractors method or manner of installation of the roof membrane during the twoyear period at contractors sole cost and expense.
The bid will be awarded to the responsible, responsive bidders whose bid, conforming to the solicitation, will be most advantageous to leon county price and other factors considered. he bid will be awarded to the responsible, responsive bidders whose bid, conforming to the solicitation, will be most advantageous to leon county price and other factors considered.
In evaluating bids, leon county shall consider the qualifications of the bidders, and, where applicable, operating costs, delivery time, maintenance requirements, performance data, and guarantees of materials and equipment. in evaluating bids, leon county shall consider the qualifications of the bidders, and, where applicable, operating costs, delivery time, maintenance requirements, performance data, and guarantees of materials and equipment.
The owner shall have the right under the contract to assess liquidated damages in the amount of **** per day for each calendar day beyond the date for substantial completion set out in the contract in which the work fails to be substantially complete due to unexcused delay. he owner shall have the right under the contract to assess liquidated damages in the amount of **** per day for each calendar day beyond the date for substantial completion set out in the contract in which the work fails to be substantially complete due to unexcused delay.
The contractor shall make the work accessible at all reasonable times for inspection by owner and the roof consultant. he contractor shall make the work accessible at all reasonable times for inspection by owner and the roof consultant.
Should roof samples be required by manufacturer issuing guarantee and if, for any reason, deficiencies are found within the samples, the contractor shall at its expense, make repairs, etc. , as necessary, to correct deficiencies and satisfy the requirements of the manufacturer issuing the guarantee. should roof samples be required by manufacturer issuing guarantee and if, for any reason, deficiencies are found within the samples, the contractor shall at its expense, make repairs, etc. , as necessary, to correct deficiencies and satisfy the requirements of the manufacturer issuing the guarantee.
If any dispute shall arise between owner and contractor regarding performance of the work, or any alleged change in the work, contractor shall timely perform the disputed work and shall give written notice of a claim for additional compensation for the work within ten 10 days after com mencement of the disputed work. if any dispute shall arise between owner and contractor regarding performance of the work, or any alleged change in the work, contractor shall timely perform the disputed work and shall give written notice of a claim for additional compensation for the work within ten 10 days after com mencement of the disputed work.
The lump sum price is subject to adjustments for work changes only as directed solely in writing by owner. lump sum price is subject to adjustments for work changes only as directed solely in writing by owner.