The City of San Antonio is seeking construction services for the District 1 Parks Multigenerational Recreation Facility 2022 Bond. Proposals are due January 27, 2026. A nonmandatory presubmittal conference is scheduled for December 15, 2025, and a nonmandatory site visit is scheduled for the same day. The project includes an addition and renovations to the West End Senior Center. The construction cost estimate is $5,650,000. 00. The contract duration is 425 calendar days. Respondents are prohibited from contacting city officials regarding the RFCSP from the time the RFCSP has been released until the contract is posted for consideration as an agenda item during a meeting designated as an A session and city employees from the time the RFCSP has been released until the contract is approved at a city council A session. The city will conduct a comprehensive, fair and impartial evaluation of all proposals received in response to this rfcsp within fortyfive 45 days of receipt of the proposals. The city reserves the right to award one, more than one or no contracts in response to this rfcsp. The selected respondent must comply with city ordinance number ****, concerning wage and hour labor standard provisions for city of san antonio construction projects amending city ordinance number 71312. The selected respondent shall furnish city with payment and performance bonds. The city will evaluate respondents price proposal. Respondents must enter price proposal in the bid form section of the civcast website. The city is interested in evaluating respondents team including subconsultantss, if applicable experience with local processes and practices, as may be evidenced by work in san antonio andor the surrounding area, during the past five 5 years. The city reserves the right to contact any respondent to negotiate a contract, if such action is deemed desirable by city.
The bid notice states that this is a 425 calendar day contract. Respondent understands and agrees that this is a 425calendar day contract.
The bid notice states that the selected respondent shall furnish city with payment and performance bonds. upon city council approval of contract award, the selectedrespondent shall furnish city with payment and performance bonds, in accordance with the provisionsof chapter **** of the texas government code required for this project have been attached hereto, incorporated by reference herein and labeled as exhibit c.
The bid notice states that the city will conduct a comprehensive, fair and impartial evaluation of all proposals received in response to this rfcsp within fortyfive 45 days of receipt of the proposals. city will conduct a comprehensive, fair and impartial evaluation of all proposals received in responseto this rfcsp within fortyfive 45 days of receipt of the proposals.
The bid notice states that the city will appoint a selection committee to perform the evaluation of the received proposals. city will appoint a selectioncommittee to perform the evaluation of the received proposals.
The bid notice states that in the event the selected respondent fails to achieve substantialcompletion andor final completion of the project by the dates established for substantial completionandor final completion, respondent hereby accepts and agrees it shall pay city the sum indicated onthe table below for each and every calendar day of unexcused delay in achieving substantialcompletion andor final completion beyond the scheduled completionfinal completion dates. in the event the selected respondent fails to achieve substantialcompletion andor final completion of the project by the dates established for substantial completionandor final completion, respondent hereby accepts and agrees it shall pay city the sum indicated onthe table below for each and every calendar day of unexcused delay in achieving substantialcompletion andor final completion beyond the scheduled completionfinal completion dates.
The bid notice states that a nonmandatory site visit is scheduled on december 15, 2025, at 3: 00 p. m. ct. a nonmandatory site visit is scheduled on december 15, 2025, at 3: 00 p. m. ct.
The deadline for submission of written questions is december 22, 2025, at 4: 00 p. m. ct. deadline for submission of written questions: december 22, 2025, at 4: 00 p. m. ct
The construction cost estimate is $5,650,**** cost estimate: 5, 650, ****.